What is the term for the sequence of activities that determines the project duration?

Study for the Landini Certified Associate in Project Management Exam. Prepare with interactive flashcards and in-depth multiple-choice questions. Each question includes hints and answers. Ace your CAPM exam!

Multiple Choice

What is the term for the sequence of activities that determines the project duration?

Explanation:
The critical path. This is the sequence of activities in the project network whose total duration is the longest, and it sets the earliest possible project completion date. Because it is the longest chain, any delay in an activity on this path directly extends the finish date, so the critical path has zero total float. Activities not on this path can have slack or float, meaning they can be delayed without necessarily delaying the project finish. Focus on the critical path helps identify where schedule risk matters most and where to apply time-saving efforts.

The critical path. This is the sequence of activities in the project network whose total duration is the longest, and it sets the earliest possible project completion date. Because it is the longest chain, any delay in an activity on this path directly extends the finish date, so the critical path has zero total float. Activities not on this path can have slack or float, meaning they can be delayed without necessarily delaying the project finish. Focus on the critical path helps identify where schedule risk matters most and where to apply time-saving efforts.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy