Quality Control Measurements can lead to which outcome?

Study for the Landini Certified Associate in Project Management Exam. Prepare with interactive flashcards and in-depth multiple-choice questions. Each question includes hints and answers. Ace your CAPM exam!

Multiple Choice

Quality Control Measurements can lead to which outcome?

Explanation:
Quality control measurements are used to check deliverables and processes against defined quality standards. When these measurements reveal deviations or defects, the natural and formal response is to propose changes to bring things back into compliance. That proposal is captured as a Change Request, which then goes through the change-control process for assessment and approval before being acted on. So, the direct outcome of quality control measurements is the creation of Change Requests to modify the project product, processes, or related documentation. (Other results like Work Performance Information can come from control quality, but the immediate, concrete outcome tied to measurement results is a Change Request.)

Quality control measurements are used to check deliverables and processes against defined quality standards. When these measurements reveal deviations or defects, the natural and formal response is to propose changes to bring things back into compliance. That proposal is captured as a Change Request, which then goes through the change-control process for assessment and approval before being acted on. So, the direct outcome of quality control measurements is the creation of Change Requests to modify the project product, processes, or related documentation. (Other results like Work Performance Information can come from control quality, but the immediate, concrete outcome tied to measurement results is a Change Request.)

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy